Location: Keswick Client Name: Cumbria Council Duration: 20 Weeks

Project Details:

Hawse End Centre is in the Lake District located in the Borrowdale Valley by the side of Derwent water, it required a complete rewire of all electrical systems within the building which includes installing a new main distribution board with multiple sub mains located around the building. It included a new addressable fire alarm system covering the building as a category L1, a intelligent emergency light system, CCTV system, IT Network and a electrical heating system.

Project Scope:

Due to the age of the building it was completely decommissioned with all the existing services strip out before we began installing the integrated system throughout the premises. The electrical rewire included several different circuits covering the lighting, sockets, kitchen, heating as well as dedicated supplies to induvial specialist systems. The heating system installed was Dimplex which as a partner we can offer an extended warranty, the intelligent light system was a Hostwave central battery system covering all aspects of the building. Outside of the building we provided feeder post for the yurts that are located next to centre all controlled from the main building.

Project Review:

At DJH Electrical we are pleased that our dedicated team of engineers completed our works package to our high standards, within the allotted timescales allowed. Our in house teams carried out all aspects of the installation and the commissioning of the electrical and integrated systems providing the client with a complete DJH package.